Home Zone project scheduled work dates

Today Alderman Colon forwarded us a message from CDOT which included the scheduled work dates of the Home Zone project.  According to CDOT, our project is scheduled to run from 7/27 through 8/6.

It looks like work will be completed in two weeks!

NO. PROGRAM WARD APPL # LOCATION BREAK DATE POUR DATE BACKFILL DATE GRIND DATE ASHPHALT PLACEMENT DATE PROJ END DATE
2 MENU BUMP OUT 35 048037 2400 N ALBANY AVE 7/27/2010 7/28/2010 8/2/2010 8/3/2010 8/4/2010

8/6/2010